New Centennial Water Source – Kaliwa Dam Project
Project Description:
Development of new water source in order to meet the increasing water demand by constructing a dam for MWSS service area’s domestic water supply.
Location:
Dam Location : Sitio Cablao, Brgy. Pagsangahan, General Nakar, Quezon / Sitio Queborosa, Brgy. Magsaysay, Infanta, Quezon
Tunnel : Traverses from the dam location to Teresa, Rizal
Project Cost:
PhP 12.20 Billion
Funding Source:
Official Development Assistance (ODA)
Status: (as of 10 September 2019)
-
Ongoing Acquisition of lots required for the Tunnel Outlet Portal
-
Ongoing coordination with the following:
-
Infanta, Real and General Nakar, Quezon Province
-
Tanay, Morong, Baras, Rizal Province
-
NCIP Region IV-A
-
DENR/EMB – Central
-
DENR IV-A
-
PAMB
-
FREE AND PRIOR INFORMED CONSENT (FPIC) PROCESS
(Jointly with the NCIP)
a). QUEZON
1st IP Community Assembly —– Completed 18 April 2019
2nd IP Community Assembly —– Completed 18 May 2019
3rd IP Community Assembly —– Completed 18 August 2019
4the IP Community Assembly (IP Concensus Building) —– No schedule yet
b). RIZAL
IP Community Assembly: Cluster 1 —— 18 September 2019
Cluster 2 —— 05 September 2019
Cluster 3 —— 12 September 2019
ENVIRONMENTAL COMPLIANCE CERTIFICATE
– 1st Procedural Screening by Review Committee —– Completed 02 August 2019
– 2nd Procedural Screening by Review Committee —– Completed 14 August 2019
– Public Hearing: Gen. Nakar —– Completed 23 August 2019
Teresa —– Completed 27 August 2019
Infanta —– Completed 28 August 2019
Tanay —– Completed 02 September 2019
– Continous meetings with DENR-EMB
LOT ACQUISITION FOR THE TUNNEL OUTLET PORTAL
– Appraisal by Land Bank —– Completed. Appraisal Report submitted 22 July 2019
– Negotiation with landowners —– Ongoing
ACCESS ROADS BY DPWH:
Access Road to Tunnel Outlet Portal (Teresa, Rizal): Construction works already completed (100%)
Access Road To Damsite (Km. 92) : DPWH Accomplishment = 35% and on-going
c). Access Road at Daraitan : DPWH Accomplishment = 7% and on-going
RESETTLEMENT
On-going coordination with DENR-IV-A , General Nakar and IPOs for the resettlement site.
OTHERS
– Workshop for the implementation of Collaborative Approach in the Management of Kaliwa Watershed Forest Reserve —– Scheduled on October 2019
———